Net structure completed on Melbourne’s West Gate Tunnel

A 38-metre-tall timber structure has been completed on one of Melbourne’s major infrastructure projects

CPB contractors has completed building an intricate timber net structure on Melbourne’s West Gate Tunnel project.

The timber structure, located at the Maribyrnong River entry and exit point to the tunnels, is made up of hundreds of timber pieces.

At 38 metres tall, it is comprised of 16 arches and will span six lanes of traffic.

  • Subscribe to our free weekly newsletter to receive the latest news in the earthmoving industry
  • Never miss a great deal and subscribe to our monthly magazine
  • Download a free copy of our latest digital magazine to catch up on the biggest news and developments in the earthmoving industry

The timber nets have been constructed at the citybound portal and westbound portal, with each spanning three lanes of traffic.

CPB Contractors project manager buildings Chris Panting says the completion was the result of a team effort.

“The team started the timber net build in early February and just eight weeks later installed the final arch at the end of March,” he says.

“In some precision lifting on site, it took four cranes and crews in elevated work platforms to install each arch and support.”

CPB Contractors is working with Transurban and the Victorian government to deliver Victoria’s West Gate Tunnel Project as part of a joint venture.

Design and construction works include:

  • Widening the West Gate Freeway from eight lanes to 12 between the M80 Ring Road and Williamstown Road
  • A 2.8km eastbound tunnel and a 4km westbound tunnel under the western suburb of Yarraville
  • A new bridge over the Maribyrnong River providing an alternative to the West Gate Bridge
  • An elevated road along Footscray Road to the Port of Melbourne, CityLink and the city’s north, and major new cycling and pedestrian path